2011 Dover Dam
Dam Safety Assurance

Problem Description

Dover Dam in Tuscarawas County was classified by the U.S. Army Corps of Engineers (USACE)  as a Dam Safety Action Class (DSAC) II structure in their nationwide screening of all USACE dams. The dam has been identified as being hydrologically deficient and unable to meet current stability criteria for sliding.

Solution Description

The plan for rehabilitation of Dover Dam consists of two parts.  First, stabilizing the dam to keep it from sliding along the riverbed involves installing anchors through the dam and anchoring the stilling basin.  Addressing hydrologic deficiency consists of installing a parapet wall and installation of a closure on the left descending bank to hold back and safely pass large flood events. In addition, the installation of bank protection on the riverbanks immediately downstream of the dam will prevent scour and erosion during passage of large flood events.

 

Grant Funding

Total estimated project cost - $68.5 million
MWCD estimated local cost-share - $2.1 million

 

Location Information

Click here for map Click here for map

Activity Log

Temporary anchors were installed through the dam early in 2008 as an intermediate measure to stabilize the structure for low to medium intensity flood events.  Construction of a project office was completed in mid-2011 at the USACE Muskingum Area Office. A contract for construction of Phase 1 of the final dam modifications was awarded by the USACE in September of 2010 to Brayman Construction, Inc.  A groundbreaking ceremony to mark the beginning of the construction phase of the Dover Dam Safety Assurance Project was held at the dam on October 26, 2010.

Construction activities began in mid-2011 consisting of the preparation of a staging area along the right downstream abutment and installation of a temporary working platform across the lower part of the ogee spillway.

Installation of 36 anchors as part of Phase I of the project was completed in the Spring of 2013.

Phase II of the project, consisting of installation of additional anchors, erosion control measures for the dam abutments, and anchoring of the spillway stilling basin is now complete.

The ribbon cutting and dedication ceremony for the Dover Dam construction project took place March 31, 2015.

 

 

Visit our Engineering page