Charles Mill Lake Shoreline Projects
2016-2017 Beach Area Shoreline
Contractor: Mark Haynes Construction Contract Price: $179,026.00 Project Length: 1709 LF Project Description:
|
...
|
2013-2014 Shoreline Area
...
|
Contractor: Tucson Inc. Contract Price: $193,002.81 Project Length: 1811 LF Project Description:
|
2010-2011 Shoreline Area
Contractor: Mark Haynes Construction Contract Price: $196,300.00 Project Length: 1667 LF Project Description:
|
...
|