Project Schedule

Months 1 & 2 (August - September)

  • Start-up Meeting / Demographics Review
  • Analysis of Existing Park Facilities, Operations, Policies and Programs
  • Needs Assessment (Stakeholders / Focus Group Meetings)
  • Develop Survey


Months 3 & 4 (October -November)

  • Continue with Facility Operations, Policies and Programs Assessment
  • Public Meetings Workshops


Month 5 (December)

  • Finalizing Assessments and Draft Report
  • Statistically Valid Survey
  • MWCD Team Meeting


Month 6 (January-February 2013)

  • Visioning , Goals and Objectives
  • Draft Recommendations / Business & Action Plans

Months 7, 8 & 9 (March - April)

  • Concepts/ Recommendations/ Public Workshops

Months 10 -11 (May- June)

  • Final Concepts/ Report/ Business Plans and Presentations